A £36.5 million contract to start work on the Borough Yard development in Birkenhead has been approved by councillors.
At Wirral Council's policy and resource committee meeting on 18 November, the committee agreed to appoint John Sisk & Son Ltd to carry out the primary enabling works.
Councillors also approved an agreement worth about £2.86m with Ion Property Developments Ltd to manage the works.
Borough Yard, previously known as Hind Street Urban Village, is planned to bring homes - up to 1,600 - to the former gasworks land between Birkenhead Central and Green Lane stations in a new development.
The next phase includes further cleaning up of the site, engineering works, installing a United Utilities storage tank for flood water and moving Cadent gas infrastructure.
The cost of the project has risen. The Local Democracy Reporting Service said a further £8.9 million is needed, which will come from the Liverpool City Region Combined Authority.
Green Party councillor Gail Jenkinson said: "We absolutely have to protect our brownfield developments and so this is such a major project going forward. By protecting the brownfield we also protect the green belt."
Labour councillor Mark Skillicorn spoke about the gap in income and life expectancy between the east and west of Wirral, and warned that not going ahead "could prove devastating for thousands of lives".
The report to the committee said not going ahead could put the funding at risk, including £2.6 million already drawn down from Homes England.
Last week we reported that councillors were being asked to approve the contract.
The same meeting considered £161.5m of transport funding for Wirral, including money moved to other Birkenhead projects.
Some planning conditions still need to be met before the enabling works can begin.